Fairground parking lot on schedule

NORMAN — Renovations on the Cleveland County Fairgrounds parking lot are running on schedule, according to District 1 County Commissioner Rod Cleveland.

“We’re coming along pretty good. We’re on schedule still,” Cleveland said.

County and contracted crews ran into some trouble when they hit utilities in the area while doing cuts into the earth and drainage work.

“We’ve hit some electric lines and water lines that weren’t deep enough,” Cleveland said. “They are private lines. We knew they were there. We just didn’t know how deep they were.”

Considering the length of time that has passed since work was done on the parking lot, hitting a few snags was not unexpected he said.

“Everything else is running great. We’re working on completion about the 5th or 20th of May,” Cleveland said. “We have a contractor that’s doing some specific drainage for us, the concrete work.”

That contractor has experienced some minor delays that pushed the project back, but nothing significant. Cleveland expects to be finished soon.

“We’ve already laid some concrete. We’ll start laying some asphalt — you’ll start seeing some blacktop out there probably next week,” he said.

Joy Hampton 366-3539 jhampton@ normantranscript.com

Text Only | Photo Reprints
Government
  • May rainfall below needed levels in state

    Norman residents looking for dry days to mow yards may think spring rains are coming frequently, but experts say those rains are less than central Oklahoma needs to pull itself out of the three-year-long drought. Lake Thunderbird’s ...

    May 19, 2013

  • Sixth annual Youth Soccer Camp starts this month

    The sixth annual Youth Soccer Camp at the Whittier Recreation Center runs from 9 a.m. to 1 p.m. May 29 through June 31 for ages 6-12. All camps are co-ed. The deadline to sign up is Thursday....

    May 19, 2013

  • City water customer says site identifying high water users is misleading

    A social media website identifying Norman residents as high water users is factually misleading, according to one Norman homeowner who made the list....

    May 17, 2013

  • New room for new judge

    Cleveland County officials are reeling with excitement over the possibility of getting a new judge, but some modifications will have to be made at the courthouse. Fortunately, a courtroom is available....

    May 16, 2013

  • City plans to shore up Rainy Day Fund

    A request from McKinley Elementary for help funding a small section of road along the school’s west side will be put back into the proposed 2013 budget, Norman City Council members decided at Wednesday’s Finance Committee meeting. Council ...

    May 16, 2013

  • Treasurer and staff honored

    Cleveland County Treasurer Jim Reynolds and six deputy treasurers were honored at the County Treasurer’s Association of Oklahoma’s Annual School, recently hosted in Norman. The seven received certificates for completing various levels of ...

    May 16, 2013

  • Legislation prevents use of welfare for strip clubs and liquor

    Gov. Mary Fallin has signed legislation that would prohibit the use of welfare cash cards in strip clubs, liquor stores and casinos. Authored by Sen. Rob Standridge, Senate Bill 667 would help ensure public assistance is ultimately being ...

    May 16, 2013

  • Sen. Inhofe secures water infrastructure victory

    U.S. Sen. Jim Inhofe, R-Tulsa, senior member of the Senate Environment and Public Works Committee, voted Wednesday in favor of S. 601, the Water Resources Development Act of 2013, which passed the Senate by a vote of 83-14. The bill ...

    May 16, 2013

  • Vote on high-density rezoning request postponed for fifth time

    Once again, a controversial high-density zoning project on Asp Avenue in Campus Corner was postponed at city hall Tuesday night. Norman residents who have showed up five times now said they are frustrated that the city council continues ...

    May 15, 2013

  • Water district still struggling to progress

    The Cleveland County Rural Water Board is still wading through bureaucratic red tape, hoping to meet target deadlines required to keep some of the grants expected to fund the infrastructure and drilling costs of the new district. It’s ...